Civil works substantially completed on Runways, Taxiways & Aprons. |
 |
Marking completed on Runway, Taxiways and Aprons. |
 |
Upper and lower forecourt works substantially completed. |
 |
Finishing works are in progress for SATS Building. |
 |
Engineering Building-Finishing & external works in progress. Block-1 handed over to Kingfisher. Block-2- Progressively being handed over. |
 |
Internal works by concessionaires completed at Menzies Building. |
 |
All the substations and Nav-aid Buildings are completed except ASR/MSSR Tower. |
 |
Construction of Railway over bridge is in progress and 99.8% of works completed. |
 |
Overall percentage completed on Airside & Landside works is 99.69%. |
 |
All works completed at Cargo Terminal Building. |
 |
Airside roads substantially completed & Landside roads are in progress. |
 |
PTB Car Park-Road works & Landscape works substantially completed. |