Roof structure and external envelope works substantially complete. |
 |
Most of Electrical & Mechanical systems are in final stages of installation and Testing, Commissioning & Integration activities are in final stages of completion. |
 |
For ATC Complex, all works completed.. |
 |
Internal Finishing works for Passenger Terminal building in progress. |
 |
Overall 97.51% of works completed on Passenger Terminal Building. |
 |
Interior works for various concessionaire areas are in progress. |