| As is evident from the above, the project work has been progressing very rapidly, once the two key milestones: Financial Closure and Notice to Proceed to EPT Contractors, were crossed subsequent to the laying of Foundation Stone in last March.
So far, about 11,771,864 cubic metres area has been cut, of which 80,85,840 cubic meters area filled to-date. As far as the Passenger Terminal Building is concerned, which includes the ATC tower, close to 15 per cent work has been completed in the last of five months or so.
Similarly, about 8 per cent work has been completed on the Airside and Landside work, which includes the Runway, in the last three months.
Way forward
During the year 2006-07, the following will be completed,
|